General Information

General Information: The pickleball court shall be a rectangle with dimensions tailored for both singles and doubles play, measuring 20 feet (6.10 meters) in width and 44 feet (13.41 meters) in length. The lines defining the court—including the perimeter and non-volley zone lines—shall be 2 inches (5.08 cm) wide and clearly marked in a color that contrasts sharply with the playing surface to ensure visibility. All court measurements are taken to the outside edge of these lines.

To enhance gameplay and reduce confusion during matches, different colors may be used to distinguish various areas of the court, such as the non-volley zone (kitchen), service zones, and boundary lines.

The minimum playing surface area required is 30 feet (9.14 meters) wide by 60 feet (18.29 meters) long. For optimal safety and movement, a recommended surrounding margin extends the dimensions to 40 feet (12.19 meters) wide by 64 feet (19.51 meters) long.

Note for Existing Installations:

  • If you already have a concrete area, please proceed directly to STEP 2.
  • If you are planning to create a pickleball court by simply painting court lines, proceed to STEP 3.

Step-by-Step Instructions

+Step 1 - Site Selection and Preparation

  1. Location:
    • Choose a flat, level area. Ensure proper drainage and install a vapor barrier (10mm thickness).
    • Select a level, well-drained area with adequate space for the court and surrounding areas.
    • Consider wind direction and sun exposure for optimal gameplay.
  2. Measure and Mark the Area:
    • Standard pickleball court dimensions: 20 feet wide by 44 feet long.
    • Allow additional space for overrun and safety zones. Aim for at least 30 feet wide by 60 feet long.
  3. Clear and Level the Site:
    • Remove any vegetation, debris, or obstacles.
    • Use a grader or similar equipment to level the ground, ensuring no dips or uneven areas.
Clear and Level Site
  1. Establish a Proper Base:
    • Excavate to a depth of 6–8 inches.
    • Fill with a 4-inch layer of compacted gravel or crushed stone for drainage.
  2. Foundation Construction:
    • Pour a concrete pad with reinforcement mesh or rebar. Ensure a slight slope (1–2%) for water runoff.
    • Cure the concrete for at least 28 days. (It's recommended to wait at least 60 days after installing concrete floors before applying any paint.)
Foundation Construction
  1. Surface Preparation:
    • Etching: To enhance paint adhesion, etch the concrete surface. For optimal etching results, we highly recommend using Max Grip as your go-to product. After etching, allow the concrete to dry thoroughly before proceeding:
      • Drying Conditions: If the temperature is around 75°F, allow the surface to dry for at least 24 hours. If temperatures are cooler, between 50-60°F, extend drying time to at least 48 hours. Below 50°F, a minimum of 7 days drying is recommended.
    • Cleaning: Thoroughly power wash the entire surface to remove all dirt, grease, and debris. For maintaining grip and ensuring a clean surface, use Maintain Grip, SlipDoctors Non-Slip Floor Cleaner, as part of the cleaning process. This product is specifically formulated to prepare surfaces for the application of coatings and treatments without compromising the grip.
    • Moisture Check: If moisture is still present after the recommended drying period, particularly in conditions below 50°F after 7 days, an outdoor waterproof membrane may be necessary to ensure the longevity and effectiveness of the coating.
Moisture Check

+Step 2 - Painting the Court Surface

Note: Preparing a New Concrete Surface

If painting a new concrete surface, it is crucial to allow the concrete to cure and dry thoroughly before application. Typically, concrete should cure for at least 28 to 30 days. Following this initial curing period, it is advisable to wait an additional 30 days for any residual moisture within the concrete to evaporate completely. Proper timing ensures the best adhesion and durability of the paint job.

Note: Repairing Existing Concrete Surfaces

For existing concrete surfaces with visible cracks or damage, it is essential to perform repairs before proceeding with painting. Begin by cleaning the area thoroughly to remove any debris or loose material. Use a high-quality concrete filler or repair product to fill in the cracks and ensure a smooth, even surface. Allow the repair material to cure according to the manufacturer’s instructions before sanding down any excess to achieve a level finish. Preparing the surface in this manner not only enhances the appearance of the paint but also improves its longevity and performance.

Paint Quantities Breakdown:

  • Court Surface: 15 Gallons
  • Court Lines: 1 Gallon

Feel free to choose alternative colors that suit your preferences.

  1. Hydro Prime Moisture Barrier: Begin by applying Hydro Prime as a moisture barrier using a low-pressure sprayer for even coverage and minimal runoff. Hydro Prime is a premium, zero-VOC penetrating sealer that strengthens, waterproofs, and primes concrete and masonry surfaces. Its vapor barrier formula deeply penetrates to reduce moisture ingress while maintaining breathability. This enhances adhesion, prevents bubbling and peeling, and ensures a durable foundation for coatings.
  2. Prime Coat Application Process: Begin by thoroughly cleaning and drying the target surface. Ensure the concrete has fully cured and that there has been no rain or sprinkler spray on the surface for several days. Apply a thin, even layer of SlipDoctors® Prime Coat using a roller or brush. Allow the primer to dry completely, which typically takes about 1–2 hours, before applying a second coat perpendicular to the first. This primer ensures enhanced adhesion and durability for long-lasting performance.
  3. Measuring and Outlining the Court: Before starting the painting process, it is crucial to accurately measure and outline the entire playing area to ensure compliance with standard pickleball court dimensions. Start by measuring and marking the outer dimensions of the playing surface area, which should be 30 feet (9.14 meters) wide by 60 feet (18.29 meters) long, including a 10-foot (3.05-meter) margin around the standard playing area for safe player movement. After marking the outer playing area, measure and outline the standard court dimensions within this area, which are 20 feet (6.10 meters) wide by 44 feet (13.41 meters) long.
  4. Marking the Court: Use a chalk line or string line to ensure straight and accurate lines. Once the perimeter is marked, use painter’s tape or a similar marking tool to create temporary lines. This will guide the paint application and help in visualizing the court layout.
Marking the Court
  1. Applying Alpha Grip Paint: Apply 2 thin coats. Applying too thick can result in bubbling. Wait 4 hours, then apply the second coat to ensure thorough coverage and protection.
Applying Alpha Grip Paint

Additional Notes for Court Painting:

  • Water Control: Ensure that sprinklers or any other water sources do not spray over the court during and after the painting process. Keeping the court dry is crucial to allow the paint to cure properly and to prevent any water damage or dilution of the paint.
  • Visibility and Compliance: It’s beneficial to use a contrasting color for the court lines against the main court color. This enhances visibility and ensures compliance with regulation standards.
  • Guidelines for Measuring and Marking: By following these measurements and marking guidelines, you ensure that the court is correctly sized and properly prepared for a professional-quality paint job that meets official pickleball standards.
  • Line Painting: After the main perimeter is established, you can proceed to add the court lines. This is covered in STEP 3. These lines include the non-volley zone, also known as the kitchen, service zones, and boundary lines. All lines should be 2 inches (5.08 cm) wide.

+Step 3 - Paint Lines

  1. Creating Lines: Before painting, ensure that the court surface is clean and dry. Measure and mark the court lines using chalk or painter's tape:
    • Court Lines: Outline the 44x20-foot area with 2-inch-wide white lines.
    • Non-Volley Zone (Kitchen): Mark 7 feet from each side of the net, creating a zone using 2-inch-wide lines.
    • Center and Service Lines: Mark the centerline dividing the court into two equal halves, and the service lines 15 feet from the non-volley zone to the baseline.
    Center and Service Lines
  2. Paint Application: Use white paint to paint the lines, ensuring they are uniformly 2 inches wide.
  3. Tape Removal: Carefully remove the tape while the paint is still wet to ensure crisp edges.
  4. Drying: Allow the paint to dry completely before using the court. It's important to follow the paint manufacturer’s recommended drying times to ensure optimal results.
  5. Drying the Court

    YOU ARE NOW READY TO PLAY!!!

Extras

Gather all necessary items

Materials Needed
Alpha Grip Anti-Slip Paint: 2 Alpha Grip White; 8 Alpha Grip Pickleball Blue; 4 Alpha Grip Safety Blue
Max Grip: concrete etch and cleaning solution
SlipDoctors Prime Coat: For concrete surfaces to ensure better adhesion
Paint Rollers and Brushes: A long-handled roller for the main area and brushes for edges
Painter’s Tape: For masking off areas not to be painted
Protective Gear: Safety goggles, gloves, and a respirator mask
Cleaning Supplies: Power washer, broom, degreaser, and mop
Mixing Sticks and Paint Trays: For preparing and holding the paint
Net and Posts
Regulation pickleball net (22 feet wide)
Net posts (durable steel or aluminum), net anchors, and tensioning system
Fencing and Boundary Protection
Chain link or mesh fencing (10–12 feet high)
Fence posts (with concrete if needed)
Gate (optional for controlled access)
Tools and Equipment
Excavator or shovel (for clearing and levelling)
Grader or plate compactor (to compact the base)
Wheelbarrow (for moving materials)
Trowel or screed board (to level asphalt or concrete)
Optional Items
LED lighting system
Benches for seating
Shade structures or umbrellas
Water station or cooler
Storage locker for paddles and balls
Miscellaneous
Safety gear (gloves, goggles, masks)
Measuring tools (yardstick, laser level, or spirit level)
Sealant (for cracks or finishing)
Garbage bags and bins (for cleanup)

Install Net System

  1. Install posts 22 feet apart (2 feet beyond the sidelines on each side).
  2. Ensure posts are sturdy and embedded in concrete if needed.
  3. Attach the Net: The net height should be 36 inches at the posts and 34 inches at the center.
  4. Use a regulation pickleball net or a tennis net adjusted to pickleball dimensions.

Surrounding Area and Accessories

  1. Fencing: Install fencing around the court (typically 10–12 feet high) to prevent balls from escaping. Use chain link or mesh material for durability.
  2. Lighting (Optional): Add LED sports lighting for evening play. Position lights to minimize glare for players.
  3. Benches and Amenities: Provide seating, shade structures, and water stations for player comfort.
  4. Court Surface Maintenance: Clean the surface regularly and repaint lines as needed. Check for cracks or wear and repair promptly.